Starliner isn’t yet ready for a crew. Just a few weeks before the Boeing-built capsule was scheduled to deliver its first passengers to the ISS, NASA and Boeing leaders announced that two major issues with the craft will delay the first crewed mission even longer.

The announcement follows a review by NASA’s Aerospace Safety Advisory Panel last week, which warned against rushing into a crewed flight before all of Starliner’s potential safety concerns could be thoroughly investigated and addressed.

The issues: In reviews late last week, the Boeing team identified two issues with the Starliner craft that could cause disaster in certain flight scenarios:

  1. Parachutes. The soft links that run from the capsule to its parachutes aren’t as strong as they need to be. If one of the three chutes doesn’t deploy, the team found that it’s likely the links to the other two could snap.
  2. Tape. There are hundreds of feet of wiring harnesses strung throughout the vehicle, and these harnesses are wrapped up in a type of glass cloth tape called P-213. Recent tests showed that this tape might be flammable in certain circumstances.

Looking back: Boeing and SpaceX were selected at the same time in 2014 to build commercial crew transport vehicles to send astronauts to the ISS. Neither vehicle met the original target of flying in 2017, but SpaceX beat Boeing to the punch, launching its first crewed mission in 2020 (and nine others since). 

Boeing has met many of the milestones for its $4.2B fixed-price contract already, having flown two test flights of Starliner so far.

Looking forward: Starliner won’t fly in July as previously planned. Boeing is spending this week figuring out exactly what needs to be done to get Starliner ready to fly again. The capsule will likely need to complete additional test flights before it can fly a crew. Boeing VP and program manager Mark Nappi declined to provide a timeline for the capsule’s first crewed mission until the team has completed its review.

Related Stories
BusinessRockets

Ursa Adds Additive With $14.5M R&D Investment

Ursa Major will buy several industrial 3D printers and hire 15 new employees for an R&D center in Youngstown, OH focused on additive manufacturing.

BusinessInternationalMilitary

The $570B Space Economy

For the third year in a row, government space budgets saw double digit percentage increases, driven by the significant militarization of space.

ISS

SpaceX is Sending a Dragon to End ISS

After over 25 years orbiting Earth, performing thousands of scientific experiments and hosting over 270 astronauts, the ISS is scheduled to be escorted out of orbit as early as 2030.

BusinessLaunch

Bill Weber Steps Down as Firefly Aerospace CEO

Firefly has tapped board member Peter Schumacher as interim CEO while leadership kicks off a search process.