Scope Creep on Artemis

Image: NASA

NASA’s Office of Inspector General (OIG) released an audit of the agency’s Artemis management. Spoiler alert: not great, but not the biggest surprise.

The big picture: The Artemis program is over budget and behind schedule. NASA provided updated timelines last week, and now, OIG is moving the goalpost again. Due to numerous technical delays, Covid, and storm damage, OIG predicts that none of the three phases of the Artemis program will proceed as scheduled. OIG’s predicted timetables: 

  • Artemis I: from November 2021 to summer 2022
  • Artemis II: from late 2023 to mid-2024
  • Artemis III: from 2024 to “several years” later—2026 at the earliest.

Budget burden: The report assessed FY2012–FY2025 Artemis costs at a whopping $93B, $25B higher than NASA’s latest estimate, and pegs SLS/Orion price per launch at $4.1B. 

  • OIG’s culprits: Sole-source, cost-plus contracts, updating contractual terms on the fly, and expendable launch/spaceflight infrastructure.

Now what? OIG made nine recommendations to NASA management to address the lapses in communication on the program’s timeline and budget. NASA leadership agreed to five and partially accepted two. They rejected two outright:

  1. To develop an annual cost estimate for the entire Artemis program
  2. To keep track of the cost per mission and establish affordability benchmarks

Related Stories
Civil

SpaceX Won’t Be Visiting Hubble Anytime Soon

Hubble has seen better days—and with NASA formally rejecting SpaceX’s commercial repair offer, that’s unlikely to change. 

CivilEO

NOAA Taps BAE Systems to Measure Hyperspectral Ocean Color

The US’ central weather-tracking agency has commissioned BAE Systems to build an instrument for its next-generation weather and climate constellation, GeoXO. 

CivilMilitary

Russia and US Face Off on Responsible Space Behavior

US leadership is frustrated with Russia’s behavior in the space domain, and they weren’t afraid to show it this week in public remarks both domestically and on the world stage.

Civil

Blue Origin’s New Shepard Flies Crew After 21 Month Hiatus

The only apparent hiccup during the New Shepard’s 25th mission came when one of the capsule’s three parachutes failed to deploy completely.